FAQs
About Transforming Cities Fund (TCF)
- two new Park & Rides
- one new rail station
- four new foot and cycle bridges
- six new or improved bus stations and interchange hubs
- new high quality cycle routes along six corridors
- bus priority along six key bus routes to create more reliable and faster bus journey times
- 800 new cycle parking spaces
- seven improvements to Rail Station Gateways
- new Real Time Information and improved passenger experience across the network.
- improve journeys by bus, rail, bike and on foot for up to 1.5 million people
- take up to 12 million car trips per year off our roads by 2036
- make 33 million rail journeys easier by improvements to rail stations
- increase bus, rail, and walking and cycling trips by up to 6%, 4% and 7% respectively by 2036
- reduce CO2 emissions by up to 1.5% / 15,000 tonnes from car travel by 2036
- create more than 1,000 jobs and add up to £1 billion to the economy by 2036
- support connectivity to 650 housing sites and 220 employment sites
What is the Transforming Cities Fund (TCF) programme?
Providing an accessible, attractive and cleaner alternative to car journeys is at the heart of Leeds City Region’s Transforming Cities Fund (TCF) - a major new programme of transport infrastructure investment secured as part of the West Yorkshire devolution deal.
The programme will be funded through £317 million from the Department for Transport (DfT) plus local match funding of up to £140 million.
In partnership with local authorities, the Combined Authority will deliver transformational infrastructure, which will dramatically improve people’s access to walking, cycling and public transport.
It is estimated TCF schemes will improve journeys by bus, rail, bike and on foot for up to 1.5 million people, take up to 12 million car trips per year off our roads and reduce CO2 emissions from car travel by up to 15,000 tonnes by 2036.
Communities across Bradford, Calderdale, Craven, Harrogate, Kirklees, Leeds, Selby, Wakefield and York are set to benefit from the schemes, which include new or improved bus and rail stations, cycling and walking infrastructure, and new Park and Rides.
What will be delivered through the TCF programme?
The programme will deliver:
Which organisations are involved?
The West Yorkshire Combined Authority is working in partnership with local authority colleagues from Bradford, Calderdale, Craven, Harrogate, Kirklees, Leeds, North Yorkshire, Selby, Wakefield and York councils on the TCF programme.
What benefits will the TCF programme bring?
It is estimated TCF will:
How is the TCF programme funded?
As part of the West Yorkshire devolution deal, the Combined Authority secured £317 million from the DfT’s TCF programme to deliver schemes in the low-cost scenario.
Since then, the Combined Authority has approved the use of future gain share funding, alongside other income streams, to deliver the high-cost scenario up to an additional £140 million.
This additional funding will help us deliver more transport improvements, which will benefit communities across West Yorkshire.
Why is this work important? / Why is this money being spent on TCF at this time?
This work is more important than ever, not only as we look to address the health and economic challenges of the COVID-19 pandemic, but also in helping us achieve our aim of becoming a net zero carbon economy by 2038.
We need to reduce car trips by 21% and increase cycling trips by 2,000%, walking trips by 78%, bus strips by 39% and rail trips by 53% if we are to achieve our ambitious net zero targets in this time frame.
The programme will connect people to economic and education opportunities through accessible, affordable, attractive and cleaner transport, boosting productivity and helping to create healthier and happier communities for the future.
Through the programme and building on the significant progress already made, we are working in partnership to transform our town and city centres for walking and cycling, improve bus reliability and journey times, and investing in our region to prepare for HS2, Northern Powerhouse Rail and the Transpennine Route Upgrade.
Who will benefit?
Communities across Bradford, Calderdale, Craven, Harrogate, Kirklees, Leeds, Selby, Wakefield and York are set to benefit from the schemes, which include new or improved bus and rail stations, cycling and walking infrastructure, and new Park and Rides.
The programme is focused on connecting people in the communities of greatest economic need with job and training opportunities. This will, in turn, help boost productivity, living standards and air quality.
When do projects get underway?
There are 22 packages of schemes, comprising 35 individual projects, within the overall programme.
Different schemes are at different stages, right through from the development of business cases and designs, to gearing up for public consultation, with Halifax Bus Station redevelopment due to start on site in spring 2021.
Find out more information at westyorks-ca.gov.uk/TCF
When will the programme of works be completed?
The schemes funded through the DfT need to be delivered by spring 2023, with schemes financed by local match funding being delivered beyond these timescales.
How is the programme impacted by COVID-19?
To date, there has been minimal impact of the programme as a result of COVID-19. The majority of the projects are at the early stages of development and much of the work required can be carried out virtually. As the schemes move to the next stage of delivery, we will continue to monitor the impact and identify any risks to delivery.
We are also looking at best practice ways of delivering public consultations and engagement activity to ensure all members of the community get the opportunity to have their say on TCF schemes during COVID-19.
The full implications of COVID-19 on the region, the economy and the transport system are still to be understood and the impact on the Combined Authority’s programmes and schemes to date has been mixed.
We are working closely with our local authority partners at every level of our appraisal process to ensure delivery timescales have taken into account the current issues and that each scheme is stress tested to ensure its ongoing viability.
In the wake of COVID-19 it is more important than ever to assess the changes to the landscapes of our towns and cities, and the impact on current and future planned schemes, particularly, but not exclusively, those relating to transport.
The impact of COVID-19 in relation to travel behaviour into and around towns and cities is assessed as part of each scheme’s appraisal.
While public transport patronage is currently lower than pre COVID-19 levels, it remains a priority to invest in public transport infrastructure to both help with economic recovery and to have the required infrastructure in place to respond to an increase in demand post-COVID-19.
As part of West Yorkshire’s devolution deal, £317 million was secured to deliver the Leeds City Region TCF programme but it will cost more than this to deliver the schemes outlined in the bid. What does this mean?
A range of options are being developed as part of each business case to determine the best scheme, which will include a range of options up to the high-cost scenario.
As part of the devolution deal, the Combined Authority secured £317 million from the DfT’s TCF to deliver schemes in the low-cost scenario.
Since then, the Combined Authority has approved the use of future gain share funding, alongside other income streams, to deliver the high-cost scenario up to £140 million.
How does TCF complement other transport infrastructure schemes being delivered across the region?
It will build on the significant investment already made through the Combined Authority’s other programmes, such as the West Yorkshire-plus Transport Fund, Connecting Leeds and CityConnect.
Many of the TCF schemes provide enhancements or extensions to the projects being delivered through these programmes, helping to spread the benefits across a wider geography.
The programme is focused on connecting people in the communities of greatest economic need with job and training opportunities. This will, in turn, help boost productivity, living standards and air quality.
For more information about the West Yorkshire-plus Transport Fund visit westyorks-ca.gov.uk/projects/west-yorkshire-plus-transport-fund
For more information about Connecting Leeds visit leeds.gov.uk/parking-roads-and-travel/connecting-leeds-and-transforming-travel
For more information about CityConnect visit cyclecityconnect.co.uk
Where can I find out more information?
Find out more information about the Transforming Cities Fund programme at westyorks-ca.gov.uk/TCF
How can I have my say on schemes in my area?
Public consultation and engagement activities are taking place throughout 2021.
Details of the TCF consultations can be found at www.yourvoice.westyorks-ca.gov.uk. You can get in touch with the Combined Authority’s Consultation and Engagement team via YourVoice@westyorks-ca.gov.uk, 0113 245 7676 or Freepost CONSULTATION TEAM (WYCA). Please note that, due to the COVID-19 crisis, the majority of the Combined Authority’s staff are working from home and there will therefore be significant delays in receiving any postal contributions. If you can, please contact the team using another method to ensure a quick response.
How was the bid developed?
The bid was led by the West Yorkshire Combined Authority in partnership with the 10 local authorities across the Leeds City Region. It was developed in two stages, with a Strategic Outline Business Case (SOBC) submitted to the DfT in June 2019. The final bid was submitted to the DfT in November 2019. The bid documents can be found at westyorks-ca.gov.uk/TCF
Who was the bid developed with?
The bid was developed in partnership with local authorities across the Leeds City Region, including Bradford, Calderdale, Craven, Harrogate, Kirklees, Leeds, North Yorkshire, Selby, Wakefield and York. The bid was also co-developed with the DfT, which provided feedback on the plans as they emerged. In line with other Mayoral Combined Authorities, we are required to feedback on the progress of the programme’s delivery.
How were decisions made around which schemes to include in the bid?
The programme is focused on connecting people in the communities of greatest economic need with job and training opportunities. This will, in turn, help boost productivity, living standards and air quality.
As part of the bidding process, the Combined Authority was asked to develop a series of schemes, which could be delivered under three different cost scenarios (low, core and high). Each scheme needed to meet the Combined Authority’s priorities, as well as objectives set out by the DfT, such as reducing carbon emissions, and increasing capacity for commuters with better access to employment centres, especially from disadvantaged communities.
Schemes put forward by local authorities were scored against the objectives before being reviewed as a programme. Once agreement had been reached between local authority and Combined Authority officers, the programme was signed off by each of the leaders, as well as members of the Combined Authority’s Transport Committee.
Bradford TCF
What are the Bradford Transforming Cities Fund schemes?
Bradford Council, in partnership with the West Yorkshire Combined Authority, is bringing forward a flagship programme of forward-thinking transport schemes, alongside major public space enhancements, that will help us shape and drive forward Bradford’s future regeneration in the city centre and beyond. Our overarching vision is to create a greener, more sustainable, accessible, and vibrant district that has immediate benefits for people living, working, visiting and studying in Bradford today, that also paves the way for future investment across the district.
The proposals being brought forward by Bradford Council will reduce reliance on car travel and contribute to reducing congestion across the district, providing cleaner air, protecting the health of local people, creating greener, more attractive public spaces and providing opportunities for regeneration. These changes will support Bradford’s ambition of becoming the UK’s leading ‘clean growth’ district and act as an enabler to the City of Culture BID.
Why have these schemes been developed?
Bradford’s Transforming Cities Fund schemes form an important part of a wider programme of forward-thinking transport and regeneration schemes being brought forward across the district that are helping us shape and drive forward Bradford’s regeneration in the city centre and beyond.
Through TCF, new public spaces and planting will be created in the city centre, to improve the look and feel of the area and make the city centre an increasingly attractive place to spend time. It will also support more cycling and walking in the city centre to better connect different areas while reducing the impact of major roads that currently dominate parts of key areas in the city centre. Achieving this is crucial to attracting more people to live, work and socialise in the city centre – increasing vibrancy, and attracting new employers to the district, bringing jobs and investment.
Bradford’s TCF programme is also essential to reducing the current reliance on car travel and subsequent congestion across the wider district, ensuring our air is cleaner air to protect people’s health. This will be crucial in fulfilling our ambition of becoming the UK’s leading ‘clean growth’ district and the wider region’s ambitions of becoming a net zero carbon economy by 2038.
Investing to improve sustainable transport options in Bradford is in everyone’s interests, making it easier for more people to get about, allowing us to grow the economy and create jobs, increase the vibrancy of our city centre, and support our City of Culture BID.
Next Steps
How far advanced are plans?
Bradford Council has so far developed early-stage proposals for the four TCF schemes aimed at improving the options in Bradford for sustainable travel and improving the local environment. We want to find out the public’s views on the scheme before progressing to the detailed design stage. We want to ask for feedback on the proposals via the public consultation to ensure that we have considered all opportunities and possible issues when looking at how and where to deliver these changes. Your feedback will help us to understand where we can make improvements to the proposed schemes and allow us to be confident that our proposals are comprehensive.
What are the next steps?
After the public consultation, the plans for the four schemes will be further developed in line with the feedback received and an Outline Business Case for Bradford TCF will be produced, which will go to the West Yorkshire Combined Authority for consideration later in the year. Once the Combined Authority have fed back on the Outline Business Case, a Full Business Case will then be developed and submitted for final approval, ahead of scheme implementation. There is a tight turn around for delivery of the TCF schemes, with all schemes required to be completed by spring 2023. Therefore, we hope to be able to begin work on the first elements in early 2022.
Will there be an opportunity to have my say again on the plans at a later date?
The current consultation is the first opportunity to comment on the form of the proposals planned for the fours schemes. People can comment by email, post, freephone telephone or online. Through the consultation, we want to gather the views of all interested and affected parties.
After the consultation, we will test and refine our plans to secure the confirmation of funding for each project. Later in the process, there will then be additional consultation to support the further design of the scheme, ahead of finalisation and implementation. Members of the public will have the opportunity to provide comments at this stage of the process also.
How soon is all this going to happen?
After the public consultation, the plans for the schemes will be further developed in line with the feedback received and an Outline Business Case for Bradford TCF will be produced, which will go to the West Yorkshire Combined Authority for consideration later in the year.
Once feedback on the Outline Business Case has been received, a Full Business Case will then be developed and submitted for final approval, ahead of scheme implementation.
The DfT element of the funding for the TCF programme has a spend deadline of spring 2023. Work is progressing to deliver schemes within this funding deadlines. We hope to be able to provide more details on proposed implementation timescales in the autumn once designs are progressed further and the scheme business case is completed for approval by the Combined Authority.